Edmund Nuttall Ltd has been awarded a contract valued at £4.2 million by the Highways Agency to undertake improvements to the communications infrastructure along sections of the M6 and M54 motorways in Staffordshire.
The contract, which has been awarded on a partnering basis, comprises the installation of a longitudinal duct system, foundations for 17 cantilever MS3s, 18 CCTV masts, a full size transmission station adjacent to the existing station at Hilton Park Service Area, the installation of equipment cabinets, matrix signal posts, emergency telephone posts and housings and the provision of safety fencing. In addition, Nuttall will install the appropriate cabling to suit the requirements of the job.
Completion of this project will take 44 weeks.
Edmund Nuttall Ltd is a group company of the Netherlands based European construction group HBG, Hollandsche Beton Groep nv.
Nuttall is currently working on a further communications contract also for the Highways Agency installing 63 CCTV cameras in various locations on the M25 motorway. This contract is valued at £6.1 million.
Peter Bishop, Public Relations Manager, Edmund Nuttall Ltd, St James House, Knoll Road, Camberley, Surrey GU15 3XW, telephone: 01276 854708, telefax: 01276 854710, email: peter.bishop@edmund-nuttall.co.uk